As the exclusive listing agents for Hoopstick Island, The Cassina Group is excited to share the latest development milestones for this one-of-a-kind Lowcountry community.
The general contractor, 3 Oaks, has completed the following work on the island since May:
As we end July:
Main Entry Progress:
Silt fencing and tree protection have been fully installed.
Clearing, grading, landscaping, and irrigation are now complete.
Landscaped areas have been temporarily stabilized with pine straw and will be sodded with Bermuda grass following construction completion.
Entry Driveway:
The subgrade for the entrance drive has been completed.
Final driveway and parking for the future mail kiosk will be added post-construction.
Island Infrastructure:
Clearing and rough grading of the main interior roadways is ongoing.
Contractors are preparing right-of-ways (ROW) for upcoming utility installation.
Community Gate:
A custom entry gate design has been finalized with the project architect and is currently being submitted for County permitting.