UPDATE: September 3rd, 2025
- Angela Tice
- Sep 12
- 1 min read
As the exclusive listing agents for Hoopstick Island, The Cassina Group is excited to share the latest development milestones for this one-of-a-kind Lowcountry community.
The general contractor, 3 Oaks, has completed the following work on the island:
From August to September:
Main Entry Progress:
All clearing, grading, landscaping, and irrigation improvements are now complete.
Landscaped areas have been temporarily stabilized with pine straw and will be sodded with Bermuda grass following construction completion.
Entry Driveway:
The subgrade for the entrance drive has been completed.
The main entry driveway apron, surface course, and parking area will be finished with the completion of the island infrastructure work.
Island Infrastructure:
All clearing and grading of the island roadways and shoulders is complete.
Utility installation began in early August and will continue through the end of the year.
Community Gate:
A custom entry gate design has been finalized with the project architect and was submitted to Charleston County permitting.