UPDATE: September 3rd, 2025

  • Writer: Angela Tice
    Angela Tice
  • Sep 12
  • 1 min read

As the exclusive listing agents for Hoopstick Island, The Cassina Group is excited to share the latest development milestones for this one-of-a-kind Lowcountry community.


The general contractor, 3 Oaks, has completed the following work on the island:


From August to September:

  • Main Entry Progress:

    • All clearing, grading, landscaping, and irrigation improvements are now complete.

    • Landscaped areas have been temporarily stabilized with pine straw and will be sodded with Bermuda grass following construction completion.

  • Entry Driveway:

    • The subgrade for the entrance drive has been completed.

    • The main entry driveway apron, surface course, and parking area will be finished with the completion of the island infrastructure work.

  • Island Infrastructure:

    • All clearing and grading of the island roadways and shoulders is complete.

    • Utility installation began in early August and will continue through the end of the year.

  • Community Gate:

    • A custom entry gate design has been finalized with the project architect and was submitted to Charleston County permitting.




 
 
 